150 kW installed in Kelowna, BC without closing the building for a day

150 kW DC

System size

Zero days lost

Downtime

Feasibility to commissioning

Scope

Installers setting ballasted racking for a 150 kW rooftop solar system in Kelowna, BC
Industry
Commercial building
Location
Kelowna, BC, Canada
Solution
Rooftop solar PV system
System capacity
Approximately 150 kW DC
Project scope
Feasibility study, site inspection, solar engineering, installation and commissioning
The challenge

This Kelowna building could not shut down. Staff and customers were in it every working day, and the owner had already been told by another contractor that a solar retrofit meant disruption.

The question was not whether solar worked here, it was whether it could be built around a business that never stops.

What Redyna did

We staged the build instead of blocking the site. Material deliveries, racking, module setting, wiring and electrical tie in were sequenced into phases with defined access routes and emergency egress kept clear throughout, so daily operations continued while the roof was being worked on.

Mounting was chosen roof section by roof section. Where the structure suited it we used ballasted racking to avoid penetrations, and mechanically secured only where conditions required it, keeping the existing roof intact under a 150 kW array.

The array layout traded a little theoretical yield for real maintenance access. Panel placement was optimised around shading while leaving service pathways, so the system can be cleaned, inspected and repaired without dismantling rows.

Project gallery
Installers setting ballasted racking for a 150 kW rooftop solar system in Kelowna, BC
01150 kW ballasted array under installation on an operating Kelowna facility.
Engineer's desk with a 3D roof model and solar energy yield calculations
02Structural load and yield calculations sized to snow loading and the local climate file.
Certified electrician securing a solar panel to roof racking
03Staged install sequencing — one roof zone at a time, no production downtime.
Hybrid solar inverter and lithium iron phosphate battery cabinet
04Hybrid inverter and battery-ready cabinet prepared for future storage expansion.
The full project record

Project overview

Redyna Technologies Ltd. developed a rooftop solar PV solution for a commercial building in Kelowna, British Columbia.

The project was designed to maximize available rooftop solar generation while working within the facility's existing electrical infrastructure and operational requirements.

The project demonstrated Redyna's ability to integrate renewable-energy systems into existing commercial buildings without major disruption to ongoing operations.

Site inspection and feasibility

The project began with a comprehensive site assessment. Redyna's engineering team evaluated:

  • Building orientation
  • Rooftop dimensions
  • Roof accessibility
  • Existing roof condition
  • Solar exposure
  • Shading
  • Existing electrical service
  • Main distribution equipment
  • Equipment locations
  • Cable pathways
  • Emergency access requirements

Establishing the configuration

The assessment was used to establish the preliminary system configuration and the installation strategy for the site.

Solar design

The solar array was designed to optimize annual energy production while maintaining appropriate maintenance access. The design incorporated:

  • High-efficiency PV modules
  • Ballasted / mechanically secured mounting structures as appropriate to roof conditions
  • String inverter architecture
  • DC protection
  • AC disconnects
  • Grounding and bonding
  • Monitoring equipment

Array layout

Panel placement was optimized to reduce shading losses and maximize available rooftop generation.

Electrical integration

Redyna engineered the electrical interface between the solar PV system and the building's existing electrical distribution system. The engineering scope included:

  • PV string design
  • Inverter selection
  • DC cable routing
  • AC feeder design
  • Protection coordination
  • Disconnect requirements
  • Grounding
  • Surge protection
  • Monitoring and communications

Installation strategy

Because the facility remained operational during construction, installation activities were planned in stages. The project team coordinated:

  1. 01Material delivery
  2. 02Mounting-system installation
  3. 03PV module installation
  4. 04DC wiring
  5. 05Inverter installation
  6. 06AC electrical work
  7. 07Grounding and bonding
  8. 08Monitoring installation
  9. 09System testing

Working around live operations

The installation methodology was designed to minimize interference with the client's daily operations.

Commissioning

Redyna performed a structured commissioning process. The system was verified through:

  • Visual inspections
  • Electrical continuity checks
  • Polarity verification
  • Insulation testing
  • Grounding verification
  • Inverter commissioning
  • Monitoring-system setup
  • Functional testing
  • Performance verification

Handover

The client was provided with system operating information and maintenance recommendations.

Project outcome

The completed solar installation provided the commercial facility with a dependable renewable-energy source and helped reduce its reliance on grid electricity. Key benefits included:

  • Onsite renewable-energy generation
  • Reduced electricity consumption from the grid
  • Improved energy sustainability
  • Remote system monitoring
  • Reduced long-term energy costs
  • Increased utilization of existing rooftop space

Engineering value delivered

The project demonstrated Redyna's capability to manage a commercial solar installation from initial feasibility assessment through final commissioning, while coordinating mechanical, electrical, installation and operational requirements.

Redyna's value — one engineering and implementation pathway

  1. Feasibility
  2. Site inspection
  3. Solar engineering
  4. Electrical integration
  5. Staged installation
  6. Commissioning
  7. Client handover
The result
  • 150 kW DC

    System size

  • Zero days lost

    Downtime

  • Feasibility to commissioning

    Scope

Have a similar problem? Talk to us.

No long intake forms. No sales team. You talk to an engineer from the first call.

NDA on request before any technical detail is shared.